The order covers the design, supply of equipment, erection, testing and commissioning of the plant for the lignite-fired Unit III at Megalopolis.
The plant is scheduled to commence operation in the second half of 2008.
Independent coverage of power generation since 1981
Public Power Corp, the Greek electrical utility, is to fit wet flue gas desulphurisation (WFGD) plant to its 300 MW Megalopolis power plant, located in southern Greece under a €83 million turnkey contract with Alstom.
The order covers the design, supply of equipment, erection, testing and commissioning of the plant for the lignite-fired Unit III at Megalopolis.
The plant is scheduled to commence operation in the second half of 2008.