The company is supplying power island equipment, namely two GT13E2 gas turbines, two heat recovery steam generators, one COMAX steam turbine and three air-cooled TOPAIR turbogenerators, along with associated supervision and commissioning, to Vietnam Machinery Erection Corp which is building the plant for PetroVietnam.
The project will be carried out in two phases, with the plant initially operating in simple cycle first by March 2008. In the second phase, further equipment will be added for full combined cycle operation later.
Related ArticlesEVN plans massive investment in power system Siemens orders for Vietnam and Korea Vietnam building programme picks up speed