The adjoining substation will be constructed by SSEM-Initec Energia Consortium for National Grid Saudi Arabia. Under a contract worth $26 million ABB will design, supply and commission a 420 kV gas insulated switchgear substation (of the type pictured) for the plant, providing a compact solution while minimising environmental impact.

The plant itself will be supplied by GE, based on F-class gas turbines, a 7F.05 and a 7F.03, in combination with a GE steam turbine. To aid fuel flexibility, the 7F.05 gas turbine will be operating on condensate gas (its first use in Saudi as a turbine fuel) and the 7F.03 on natural gas, with Arabian Super Light (ASL) crude oil as backup. The generators, heat recovery steam generators, condenser, boiler feed pumps and a Mark VIe distributed control system will also be supplied by GE.