"We have had good progress. They are installing an average of three foundations per week, but in this area we are of course at the mercy of the weather," says Svein Aage Gurrik, who is in charge of the Dudgeon project's marine operations.

A2SEA's Sea Challenger is installing the wind farm. At first, the vessel will act as accommodation for the project, from September until turbine installation starts. The load out port will be Hull.