Chonburi mega plant completed

12 January 2023



The fourth and final M701JAC-based single shaft combined cycle unit at the Chonburi natural gas fuelled mega CCGT plant in Thailand entered operation on 1 October 2022. The plant, about 130 km southeast of Bangkok, is owned by a joint venture of Gulf Energy Development PCL and Mitsui, and operated by Gulf SRC Co Ltd.


Above: Chonburi combined cycle plant

This milestone signals completion of one of two 2650 MW M701JAC-based CCGTs power plants that Mitsubishi Power is supplying in Thailand, for which turnkey orders were secured in 2018. Construction of the second, to be operated by Gulf PD Co Ltd, is currently underway in Rayong Province.

In September 2022, the M701JAC gas turbine of the first Chonburi unit achieved 8000 actual operating hours (AOH), establishing what Mitsubishi describes as “an industry benchmark of reliability.”



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.