Clearing the way for Finland’s next nuclear power plant

26 March 2018



In a remote part of northern Finland, Fennovoima is pressing ahead with plans to build a 1200 MW Russian-designed VVER-1200-based nuclear power plant, Hanhikivi 1, named after the peninsula upon which it will be located. Caroline Peachey, editor of Nuclear Engineering International


The Hanhikivi 1 project began in 2007 with the setting up of Fennovoima, a not-for-profit co-operative of power companies and industry, established under the Mankala business model that is employed in the Finnish electricity sector. Fennovoima will produce electricity for its shareholders at cost price – estimated at a maximum of €50/MWh, or around half the price of the UK’s Hinkley Point C project, which is being built on a similar schedule for startup around 2025.

Does Finland need nuclear?

This year, nuclear power is expected to account for some 30% of the electricity produced in Finland, according to Jorma Aurela, chief engineer at the Ministry of Economic Affairs and Employment. Finland has two operating nuclear plants, two 880 MW boiling water reactors at Olkiluoto and two 488 MW Russian-design VVER reactors at Loviisa, plus a 1650 MW EPR unit under construction at Olkiluoto. Olkiluoto 3, which is being built by an Areva-Siemens consortium under what was described as a “lump-sum turnkey” contract, was initially expected to start operating in 2009. But it has been hit by repeated delays and is now targeting regular electricity production in May 2019. The additional delay means that Finland will be facing two “hard winters,” Aurela says. Thankfully, the overall impact of the slowdown has been limited.

Over the last decade, Aurela says that Finnish electricity demand has fallen from around 90 TWh to 80 TWh. Meanwhile, electricity imports have risen to make up for the delays in bringing Olkiluoto 3 online. As it stands, domestic energy production in Finland is not sufficient to cover electricity consumption, and the country imports almost a quarter of its electricity from the Nordic market. The limited electrical transmission network means that imports cannot increase much beyond this amount. Plus, with Germany and Sweden looking to phase out nuclear power and considering the variability of hydro and wind energy in the region, there is potential for a supply shortfall during peak periods. There are also climate considerations.

Aurela confirms that Finland is committed to phasing out coal by 2020 and that the government is “strongly committed” to biomass. Finland has a target of achieving 30% of electricity production from renewables and biomass by the end of the decade, while hydropower is expected to continue providing 10-15% of the country’s electricity. Once Hanhikivi comes on line, after 2024, the share of nuclear power in Finland’s electricity mix could reach 40-45%, although this depends whether Loviisa 1&2 are licensed to operate beyond 2027 and 2030.

Scale down, and switch to VVER

In January 2009, after spending two years investigating potential sites and carrying out environmental impact assessments, Fennovoima applied to the Finnish government for a decision-in- principle to build a new nuclear power plant. The application was based on a one- or two-unit plant supplied by Areva or Toshiba, located in Pyhäjoki or Simo. In July 2010 parliament voted in favour of Fennovoima’s proposal as well as TVO’s plan to build a fourth reactor at Olkiluoto. Fortum, however, received a negative decision on its proposed Loviisa 3 project.

In October 2011, Fennovoima chose Pyhäjoki over Simo as the preferred site for its plant due to more favourable bedrock and seismic characteristics. Work on the project continued, but it faced a setback in October 2012 when German utility E.On, which had a 34% stake in the project from the outset, pulled out after choosing to end all business in Finland.

Fennovoima then began evaluating the potential to scale down the project from 1600 MW to 1000-1300 MW. In December 2013, Fennovoima signed a plant supply contract with Russian nuclear company Rusatom Overseas for a power plant with a VVER-1200 reactor.

Another agreement established that Rosatom (parent company of Rusatom) would take a 34% share of Fennovoima (through its Finnish subsidiary Raos Project) and that it would help arrange finance for the plant. The deal was completed in March 2014, and Fennovoima applied to the government to change the design of the unit to a VVER-1200. The government agreed in September, provided that at least 60% of the company’s shareholders were Finnish upon submission of the Hanhikivi construction licence application.

Fennovoima submitted its 250-page construction licence application to the Finnish Ministry of Employment and Economy in June 2015. By that point, Finnish ownership in Fennovoima stood at over 60%.

Economics and localisation

The cost of the Hanhikivi project is estimated at €6.7bn, and of this, roughly €2bn will stay in Finland with local consultancy and construction work, says Minna Forsström, Hanhikivi 1 project director. But Fennovoima has no specific target for project localisation. Fennovoima CEO Toni Hemminki says that around a quarter of the project cost would be provided by equity contributions from project shareholders, with the rest coming from debt financing by Rosatom. The first half of the financing package was agreed in 2015, but the second half remains under negotiation and is expected to be covered by Export Credit Agency guarantees and other sources.

The project is expected to have a significant impact on the national economy. Once in operation, the plant will increase the gross national product by over 0.25%, according to a study from VTT, Finland’s Technical Research Centre. The impact on the Finnish economy could reach €500 million a year, with Pyhäjoki region expected to receive €4.2 million in annual real estate taxes.

The Arabelle steam turbine (with HP, IP and three LP stages) and Gigatop 4 generator for Hanhikivi 1 will be provided by GE (which acquired these technologies with its purchase of the Alstom power businesses in 2015).

Rolls-Royce and Schneider Electric have been chosen as preferred automation suppliers, subject to final contract negotiations, with Rolls-Royce main supplier and provider of safety systems including digital protection and Schneider Electric providing operational I&C systems. The early selection of automation providers was essential for the progression of nuclear power plant design work and licencing.

Current priorities

The focus of Fennovoima’s work in 2018 will be the delivery of the construction licence documentation, site preparation and recruitment for the Fennovoima organisation, says Minna Forsström. The company also hopes to start procurement of the long-lead items, such as the reactor pressure vessel and forgings, which will be made in Ukraine by Atomenergomash, Rosatom’s equipment manufacturing and engineering arm.

The licence documentation, all submitted in English, gives a general description of the site, plant type, safety systems and operating organisation. Review of the construction licence application by the Finnish Radiation and Nuclear Safety Authority (Stuk) is expected to take at least two years.

Stuk also approves the major suppliers and their management systems, something that differs from the rest of the world, notes Forsström. Plus, Stuk is able to conduct unannounced inspections of Fennovoima or its supply chain. 

In September 2017, Fennovoima revealed that it is not expecting to receive the construction licence until 2019, but the impact this will have on the overall schedule remains unclear. Forsström says that Fennovoima’s Russian partners play a “major role” in preparing the construction licence application documents. Fennovoima reviews them and submits them to Stuk for review. Stuk then makes comments and sets out additional requirements before approving them. As such, licensing submittal is “an everyday action” says Forsström.

Liisa Heikinheimo, deputy director general of Finland’s Ministry of Economic Affairs and Employment, presented, on 10 October 2017, a revised schedule of work being carried out by Stuk. It shows that reviews of the Hanhikivi 1, Olkiluoto 3 and Posiva repository licence applications are being carried out simultaneously, alongside other regulatory work.

“The target for operation remains 2024 even though there have been some discussions with Rosatom regarding the schedule,” says Forsström.

At the moment Fennovoima has 350 employees of over 20 nationalities, with around 30 staff located at the site. There will be maximum of 500 personnel once the plant starts operating. Forsström says that during the project over 25 000 workers are expected to pass through the training building, and up to 4000 people could be working on the project simultaneously during the construction phase. Fennovoima is upping its recruitment drive, but Hemminki says the company is not facing any significant recruitment or skills challenges (a much discussed topic for the nuclear industry generally).

Forest site

The 546 km2 Pyhäjoki region is sparsely populated, home to about 35 000 people. Nature is at the heart of life, with hunting, fishing and berry picking all popular activities.

Initial site preparation works focused on cutting down trees, bringing electricity and water to the area as well as building and strengthening roads. Construction of the 4 km Hanhikiventie road started in September 2014 and was completed the following October. Taking into account lessons from Japan’s Fukushima Daiichi accident, the road has been raised 4.6m above sea level to ensure access to the site in case of flooding or natural disaster.

The focus of construction has now shifted to excavation works for the cooling tunnels, reactor foundation and buildings.

Fennovoima will invest €400-500 million in the project, before construction of the nuclear island begins, according to Jouni Sipiläinen, construction director for Hanhikivi.

Work is being carried out with the environment in mind; rare plant species have been protected, and some species of moor frogs relocated. Fennovoima is also aiming to reuse 85% of the waste generated during construction, says Sipiläinen. The site waste sorting station will be operated by Rosatom, with Fennovoima responsible for transport of materials.

Construction of 21 two-storey accommodation buildings for 1000 workers is underway, while the training building and main gate building have already been completed. Fennovoima is also erecting a weather mast at the highest point on site, 120 m above sea level. According to Sipiläinen, there is a requirement to collect weather data, such as wind speed, for three years before nuclear fuel can be loaded into the reactor.

Two concrete batching plants, with a capacity of 120m3/h, have also been finished, and testing is underway. The concrete is to be supplied by Finnish company Ruskon Betoni.

The depth of the foundations will vary from -7m to -16m, with the cooling water pumping buildings to be located 25m below sea level.

In September 2016, Terramare Oy started dredging and hydraulic engineering work for the harbour and cooling water intake structures. By mid-October, blasting works for the water intake and jetty area had finished for 2017, but were set to resume for another couple of months in the spring of 2018.

Work on a €10 million administration building is also underway. Fennovoima signed an agreement for the detailed design of the facility in October and aims to launch a tender next spring, for construction to begin in summer 2018. Once completed in early 2020, Fennovoima will prepare to move its headquarters from Helsinki to Hanhikivi.

Second unit?

While just one reactor is currently planned for Hanhikivi, an area of land has been reserved for a second unit, should the company decide to expand the project. 

Nuclear VVER-1200 reactor and Arabelle steam turbine
Nuclear Photograph of the peninsula today
Nuclear Visualisation of the new nuclear plant
Nuclear Location of Pyhäjoki region, where the new reactor is to be sited


Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.