combined heat and power

First UK 9FB imminent at Immingham

1 October 2009



The completion and commercial start up of the extension to the Immingham combined heat and power plant in the northeast of the UK is due for Q4 2009. Total output of the combined plant will be 1180 MW, making it one of the largest such plants in the world. It will also feature the first installation of a GE 9FB gas turbine in the UK.


ConocoPhillips has stated that its Immingham combined heat and power plant in northeast England, on the same site as its Humber oil refinery, was ‘progressing the commissioning and start-up work of its 450 MWe Phase II expansion’ to an expected date in Q4 but gave no exact date or month. This is a few months later than the originally projected start date of summer 2009.

The plant, which commenced commercial operation in late 2004 and is one of the largest, cleanest and most efficient of its type in Europe supplies steam and electrical power to the Humber oil refinery and steam to the Total Lindsey oil refinery, two of the largest in the UK, on the adjacent site in North Lincolnshire.

In October 2006 ConocoPhillips announced approval of an investment of approximately $400m (£320m) to expand capacity at the ICHP from 730 MW to 1180 MW. Then in January 2008 the plant was put up for sale at a price of £500 million, a move that Conoco described as routine asset assessment, but it was at pains to assure prospective buyers that the extension plan would not be affected. Nor was it.

This capacity addition will make Immingham CHP one of the world’s largest and most efficient power stations, although a study to determine the economic feasibility of modifying the enlarged plant to utilise gasification technology, enabling it to operate as a ‘clean coal’ facility, was deferred when the UK government decided last year to exclude gasification from its clean carbon competition.

Main components

The original 734 MWe plant (see schematic below) has four boilers (two HRSGs and two auxiliary boilers) sharing a single four-flue chimney. The plant is designed to operate in several different modes, exporting anything from 150 MWe to 734 MWe to the grid, while maintaining steam supply to the two refineries. It is equipped with two 260 MWe GE 9FA gas turbine generating sets, each exhausting into a Nooter Eriksen HRSG. Both of the HRSGs have extensive supplementary firing, and in addition there are the two auxiliary boilers. The plant has two Franco Tosi supplied steam turbines, which also generate electricity (115 MWe each), and from which steam is extracted at 50 bar for refinery use. The power plant internal house load is around 20 MWe.

The extension, for which the main contractor is Black & Veatch, is centred on a single GE 285 MW 9FB gas turbine exhausting into an HRSG which supplies steam at 100 bar to the common header. After being expanded through a 200 MW Toshiba steam turbine steam is fed to the 50 bar common header supplying the refineries. Several links between the 50 bar and 100 bar headers ensure continuity of steam supply. Electricity production will remain heat demand led.




Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.