GNA II on target for 2025

12 January 2023



Construction is underway at the GNA II LNG-fuelled combined cycle power plant in Brazil, with commercial operation planned for January 2025. Under a contract placed earlier this year, SENER has similar scope on GNA II to what it had on GNA I, which entered operation in 2021. This scope focuses on basic and detailed engineering and aims to achieve complete multidisciplinary integration between GNA I and GNA II, which will have a combined installed capacity of some 3 GW, and the associated LNG terminal. The facilities are located in the Port of Açú, State of Rio de Janeiro.


GNA II, 1.6 GW, will employ three Siemens Energy HL gas turbines plus a steam turbine. GNA I employs the same 3-on-1 configuration but uses Siemens Energy H class GTs.

GNA, Ga´s Natural Ac¸u, is a joint venture of Prumo Logi´stica, BP, Siemens, and SPIC Brasil.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.