Five Caterpillar gensets are providing 2.8 MWe for the new El Corte Ingles shopping centre in Madrid. Three gas-fuelled Caterpillar engines are scheduled to expand the power capability to 6.0 MWe.

El Corte Ingles draws a base load of 2.0 MWe from the grid, supplementing additional power needs with the power plant. Hot water from the engines' exhaust and cooling jacket is used as part of a combined heat and power and absorption chiller system. Cooling water at 99oC is passed through an absorption chiller to produce all the complex's air conditioning needs.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.