Uncertain future for combined cycle

26 March 2021



The combined cycle plant has been the power industry’s workhorse for a decade, and has evolved to fill a niche in a power portfolio with large proportions of renewables. But are its days numbered?


Above: Centrica’s Brigg facility employs Wa¨rtsila¨ gas piston engines

 

In October 2018, UK utility Centrica started up its new gas-fired power plant. But this did not use gas turbines, for so long the utility’s workhorses. Instead, it had invested £180 million in two 49.8 MW gas engine arrays, at its Brigg and Peterborough sites.

The engine array at Brigg and the fate of a CCGT at the same site illustrate how Centrica’s strategy has changed. The original Brigg plant, which started up in 1993, was a 240 MW CCGT designed to run on baseload. Now the steam part of the cycle has been decommissioned, with the steam turbine removed in 2016. The remaining plant operates as an OCGT, rated at just 99 MW. Even at this lower rating, it has been operating for only 3% of the time in winter and as little as 1% of potential hours in summer (150 hours in total in 2017). The ageing plant could have 10-15 years of technical life remaining, but its economic life could be far shorter.

The choice of a reciprocating engine array is partly driven by its lower cost and risk profile: below 50 MW the GB planning and permitting regime is much simpler, construction is quicker and hence price risk is lower and the engine arrays can be built on existing industrial land. But equally important is that gas (piston) engine proponents say they can respond better to the needs of power systems with high renewables penetration.

The gas reciprocating engines at Brigg take two minutes to come to full load, compared to 20 minutes for the 99 MW OCGT plant. For both plants those figures are from hot start – they require the plant to be already warmed to at least 60°C. But unlike the gas turbine, the gas engines can be warmed electrically – using 100% renewable electricity from the grid, so
at zero cost of carbon for staying in reserve. These characteristics are attractive to the system operator, NGESO, which wants fast response and reserve options with low carbon emissions.

What is more, the new engines have a ramp rate of 15 MW/minute – twice the rate of their neighbour – and their efficiency is about 45%, compared with about 25% for the OCGT. Gas engines can in general also stop more quickly – within one minute, according to engine supplier Wa¨rtsila¨.

Brigg is an example of how the market for gas generation is changing in GB – and other countries are likely to take the same route.

GB invested heavily in combined cycle plants in the 1990s and for nearly two decades they became a mainstay of the generation fleet. They were more flexible than GB’s nuclear plant, and they gradually knocked coal out of the merit order as the cost of cleaning up pollution from coal plants – SOx, NOx, particulates, etc – began to weigh heavily on coal even before it started to bear the burden of carbon costs.

But now, in its turn, large scale gas is being driven out of the merit order, replaced with renewables at zero marginal cost.

It all adds up to a shrinking market for gas turbines. Manufacturer Siemens said early this year that the global demand for large gas turbines is expected to shrink to 110 turbines per year, compared to the industry’s current total manufacturing capacity of around 400 turbines.

It also makes the sale of Rolls-Royce’s Bergen medium-speed engine subsidiary of keen interest. The company announced it would dispose of the factory in March this year and it has now appointed Deloitte to carry out the sale. Rolls Royce said that in CHP mode, these engines can reach an efficiency of over 95%. Their niche – previously described by Rolls Royce as district heating or industrial applications, where heat is used locally and the electrical power is either consumed locally in a micro grid or exported to the grid – may prove attractive to buyers.

These engines are sold as enabling the energy transition, “providing balance and backup power to the grid, or as the back-bone of microgrids”. Competition with well-known names like Caterpillar is likely to be fierce – with incumbents having a business model that turns out hundreds of engines each year, with financing and lease packages alongside the technology.

Propped up by a capacity market

Gas engines have been propped up in GB by a capacity market as well as by ancillary service payments. GB government was concerned from the start that having a large tranche of renewables – at zero marginal cost – would undermine the business case for gas generation and in response it instituted a capacity market that awarded availability fees to qualifying plant, first excluding and later heavily discounting renewables. The CM was implicitly intended to support new large gas plant. But in the auction for CM contracts, new gas reciprocating engines were able to price under gas turbines, not least because by sizing at 49 MW they circumvented GB’s costly planning and permitting regime for large plant and they could be built quickly – and the plans relatively easily abandoned in the event they did not win a CM contract.

Over the years several GW of gas engines arrays have come forward to bid into the CM and they – along with previously little-considered onsite generation, interconnectors and other less capital intensive capacity – have driven CM prices down far below what is needed to underwrite new gas turbines (generally considered to be around £35/MW) and on occasion as low as below £1/MW.

In practice the CM has brought forward just one CCGT, ESB’s Carrington plant, but it has underwritten not only gigawatts of gas reciprocating engines but also gigawatts of battery storage. And there lies a new competitor for gas combined cycle.

 

Above: Array of containerised Jenbacher gas piston engines, Ashford, UK (photo: Clarke Energy)

 

Propped up by ancillary services

Gas turbines have found it hard to make money on energy sales but in recent years their finances have been supported by an important role providing ‘ancillary services’ to GB system operator NGESO.

Within a high-renewables system the ability of gas turbines to provide system inertia – helping maintain frequency and voltage and improve fault ‘ride-through’ – by sheer weight of rotating machinery, has been well rewarded.

That role has been exceptionally important over this Covid summer. With industry and commerce temporarily closed, suppressing demand, and better than average supply from wind and solar, NGESO found itself battling to maintain grid stability. It had to artificially raise demand by several GW and constrain off wind – at considerable cost – so it could bring on thermal plant (biomass as well as gas turbines) to raise inertia.

NGESO found it a useful experience that provided insight into how it will manage a future system with an equally high proportion of renewables. But it left the system operator unshakeable in its belief that it would by then be able to manage the system without fossil use.

It was an ambition that had been announced by NGESO in 2019 and it should have come as an unpleasant shock to gas turbine operators who had been the industry’s ‘go-to guys’, offering balancing, reserve, black start and inertia services. NGESO set 2025 as the date by which it wants to be able to operate the grid with all those services from other sources – renewables, storage, demand side response etc – and balance it without fossil plant so long as there is enough low-carbon generation in operation. (Managing weeks-long low-wind periods is a different problem and one that requires a different solution.)

For all that gas turbines have done to talk up the flexibility they can bring to the system, the fact is that they are not best placed to do it. In open markets for ancillary services, gas turbines will often be beaten. Now, they are being beaten by gas reciprocating engine arrays. Increasingly they are being beaten by batteries offering synthetic inertia or sub-second response. This autumn NGESO launched a so-called Dynamic Containment response product which it says, “will kick into action in under a second to manage the imbalance in the frequency.... Batteries’ speed and flexibility make them particularly well-suited to the task, but any technology type can take part and we anticipate a wider range of providers participating in the future.”

It is happening in GB – other countries will take a similar path.

In fact, GB is behind the pace in some ways. It has sought a derogation from the EU’s new Electricity Market Directive, which requires ‘gate closure’ – when power contractors stop trading for a particular delivery period – no more than 15 minutes ahead of dispatch. GB incumbents complain of the capital cost of moving from the current half-hour trading intervals. But that is also a protection for incumbent plant; the closer to real-time the gate closes, the sharper are the price signals for market participants and the better rewarded plant that can flex or start up on the minute.

Wa¨rtsila¨ says its US customers start up their gas recip units up to eight times a day, sometimes for just 15 minutes, while Germany is considering moving to a five-minute gate closure. Gas has been the fast-response plant for the last decade but now it is being superseded with options that are faster and emit less carbon.



Linkedin Linkedin   
Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.