The 800 MW plant is due for commissioning is scheduled for 2007. The value of the contract, including the simultaneously signed long-term service agreement, is approximately €400 million.
Siemens will supply two gas turbines, one steam turbine, three generators, two heat-recovery steam generators, and the entire mechanical and electrical equipment. Advanced instrumentation and control systems supplied by Siemens will also be installed. In addition, the company will handle gas turbine maintenance for a period of up to twelve years.