The order comprises of delivery, commissioning and a two-year service and maintenance agreement. The 18 units will be installed at three project sites each of which will comprise of six turbines with a total installed capacity of 9.9 MW. Delivery is scheduled for the autumn of 2008 and commissioning is expected to be completed in December 2008.